Plan a sprint with capacity estimation, story selection, dependency mapping, and risk identification. Use when preparing for sprint planning, estimating team capacity, selecting stories, or balancing sprint scope against velocity.
## Content
## Sprint Planning

Plan a sprint by estimating team capacity, selecting and sequencing stories, and identifying risks.

### Context

You are helping plan a sprint for **$ARGUMENTS**.

If the user provides files (backlogs, velocity data, team rosters, or previous sprint reports), read them first.

### Instructions

1. **Estimate team capacity**:
   - Number of team members and their availability (PTO, meetings, on-call)
   - Historical velocity (average story points per sprint from last 3 sprints)
   - Capacity buffer: reserve 15-20% for unexpected work, bugs, and tech debt
   - Calculate available capacity in story points or ideal hours

2. **Review and select stories**:
   - Pull from the prioritized backlog (highest priority first)
   - Verify each story meets the Definition of Ready (clear AC, estimated, no blockers)
   - Flag stories that need refinement before committing
   - Stop adding stories when capacity is reached

3. **Map dependencies**:
   - Identify stories that depend on other stories or external teams
   - Sequence dependent stories appropriately
   - Flag external dependencies and owners
   - Identify the critical path

4. **Identify risks and mitigations**:
   - Stories with high uncertainty or complexity
   - External dependencies that could slip
   - Knowledge concentration (only one person can do it)
   - Suggest mitigations for each risk

5. **Create the sprint plan summary**:

   ```
   Sprint Goal: [One sentence describing what success looks like]
   Duration: [2 weeks / 1 week / etc.]
   Team Capacity: [X story points]
   Committed Stories: [Y story points across Z stories]
   Buffer: [remaining capacity]

   Stories:
   1. [Story title] — [points] — [owner] — [dependencies]
   ...

   Risks:
   - [Risk] → [Mitigation]
   ```

6. **Define the sprint goal**: A single, clear sentence that captures the sprint's primary value delivery.

Think step by step. Save as markdown.

---

### Further Reading

- [Product Owner vs Product Manager: What's the difference?](https://www.productcompass.pm/p/product-manager-vs-product-owner)

## Related Skills

- [brainstorm okrs](https://6ducklearn.com/skills/brainstorm-okrs/index.md): Brainstorm team-level OKRs aligned with company objectives — qualitative objectives with measurable key results. Use when setting quarterly OKRs, aligning team goals with company strategy, drafting objectives, or learning how to write effective OKRs.
- [create prd](https://6ducklearn.com/skills/create-prd/index.md): Create a Product Requirements Document using a comprehensive 8-section template covering problem, objectives, segments, value propositions, solution, and release planning. Use when writing a PRD, documenting product requirements, preparing a feature spec, or reviewing an existing PRD.
- [dummy dataset](https://6ducklearn.com/skills/dummy-dataset/index.md): Generate realistic dummy datasets for testing with customizable columns, constraints, and output formats (CSV, JSON, SQL, Python script). Use when creating test data, building mock datasets, or generating sample data for development and demos.
- [job stories](https://6ducklearn.com/skills/job-stories/index.md): Create job stories using the 'When [situation], I want to [motivation], so I can [outcome]' format with detailed acceptance criteria. Use when writing job stories, creating JTBD-style backlog items, or expressing user situations and motivations.
- [outcome roadmap](https://6ducklearn.com/skills/outcome-roadmap/index.md): Transform an output-focused roadmap into an outcome-focused one that communicates strategic intent. Rewrites initiatives as outcome statements reflecting user and business impacts. Use when shifting to outcome roadmaps, making a roadmap more strategic, or rewriting feature lists as outcomes.
- [pre mortem](https://6ducklearn.com/skills/pre-mortem/index.md): Run a pre-mortem risk analysis on a PRD or launch plan. Categorizes risks as Tigers (real problems), Paper Tigers (overblown concerns), and Elephants (unspoken worries), then classifies as launch-blocking, fast-follow, or track. Use when preparing for launch, stress-testing a product plan, or identifying what could go wrong.